Black Cat roundabout project will feature a second cat statue

The end is in sight with the Black Cat roundabout upgrade on schedule to finish on time and within budget.

And people will be delighted to know that the famous Black Cat metal landmark will return – and will be joined by a friend in readiness for completion of the scheme in spring 2027.

The famous Black Cat roundabout landmark will feature two black catsplaceholder image
The famous Black Cat roundabout landmark will feature two black cats

Gareth Moores, project director of the A428 Black Cat to Caxton Gibbet project, said the future of the Black Cat figure was one of the most common questions asked by people enquiring about the project.

He told MP Richard Fuller that a working group had looked at the question of the popular landmark but, due to the size and complexity of the project, it has been difficult to identify where to place it.

In an interview to update the MP on the project, Mr Moores revealed: “Well, I can give you an exclusive on the black ‘CATS’ plural. So this has been the most frequently asked question on the project, not are you on time or are you on budget, but where is the cat going?

"We’ve actually had a working group, working with the local community, some of the people involved with the original black cats, and a decision’s been taken to put two black cats on the roundabout.

"It’s a really popular local landmark and, due to the size and complexity of the new roundabout structure and overbridges we haven’t been able to identify anywhere it could be placed where you can see it from everywhere. So a decision’s been taken that we will use the original black cat and get an exact replica and place them on opposing quadrants so they can be seen from all elements of the roundabout.”

Mr Moores also confirmed the roundabout will retain its original name and still be called the Black Cat roundabout, not Black Cats roundabout.

The interview also gives an update on the timing for completion and what there is left to do.

Mr Moores said the scheme was two thirds of the way through, still on time and on budget. He said some ‘key stuff’ going on at the moment included lifting beams on to the main A421 structure. The beams are 55 tonnes and being lifted into place by a 600 ton crane.

He also admitted the hot weather had affected the work schedule but that safety of workers, involving a maximum number of 1,200, to date, had to be a priority.

While confirming the project was on schedule for opening of the A421 in spring 2027 Mr Moores said the opening of the A1 underpass would be delayed eight to ten weeks but that the impact would be minimal.

A big clean up operation will then follow and include replacing topsoil, landscaping and planting.

You can view a video of the interview here

> The latest road closures and diversion routes at the Black Cat junction are scheduled for between 9pm Friday, August 21 and 5am Monday, August 24.