Cadent to upgrade 400 metres of gas pipes from the 60s right across Ampthill
Work has started today (Monday) 27 July to replace old gas pipes from the 60s.
It will be carried out in phases and is expected to last SIX WEEKS until Monday, September 7.
400 metres of gas pipe – originally laid in 1960 – will be replaced with modern plastic pipes.
Obviously, with all this work, there will be a series of road closures as well:


Phase 1 will involve a road closure on Saunders Piece from the junction of Preston Close to the junction of Queen’s Road
Phase 2 will take place on Brinsmade Road
Phase 3 will involve a road closure on Saunders Piece from the junction of Queen’s Road to the junction of Lea Road
Phase 4 will involve a road closure on Queen’s Road at the junction with Oliver Street
Phase 5 will involve a road closure on Oliver Street from the junction of Queen’s Road to the junction of Houghton Close. Work could also affect Chiltern Close
Gas stays ON for the duration of work. The only interruption to supply will be to properties that take a direct feed from the pipes being replaced. Supply to these properties will be disconnected for a short while, as the property gets connected on to the new pipe. Advance notice will be given, and more info will be provided to these properties.
If you smell gas, always ring the National Gas Emergency Service immediately on 0800 111 999, day or night. Do not assume it is related to this work; it may not be and needs to be checked.